May the Holiday Warm Hearts: Idram and IDBank Support the Children of Heroes Beneficiaries of the "By Your Side" program at IDBank AraratBank Named Large CSR Company of the Year Idram Joins the Fight Against Food Insecurity Ucom’s Renovated Sales and Service Center in Yerevan Mall Reopens 1% idcoin instead of New Year’s suffering: practical tips Idram Junior Donated Books to Schools Big Christmas Market with Idram, IDBank and idplus Ucom Supports Wildlife Monitoring in Ararat Region IDBank, Idram, and idplus at the Big Christmas Market Converse Bank Deputy CEO and CFO, Grant Akopian, Elected to BACEE Board Ucom and SunChild NGO Install a Solar Plant in Alaverdi Kindergarten
DIALOG Organization - Partner of the “Born in Artsakh” ProgramMoody's upgrades Converse Bank's ratingsAraratBank participated in the WEPs regional experience-sharing workshopIDBank issues the 3rd, 4th and 5th tranches of bonds of 2025AraratBank: Special Rate for SWIFT Transfers up to EUR 20,000 IDBank Opens a New Branch at Homplex MallUcom Launches 5G Network in Abovyan and EjmiatsinCustomer Appreciation Day at IDBank AraratBank Joins BAFT Association Over AMD 12 Billion Provided by AraratBank in 2024 to Support the MSME Sector Ucom’s General Director Joined the International CirculUP! Forum to Foster Circular Innovation in Armenia IDBank Representative Joins the Editorial Board of Trade Finance Global DIALOG Organization - Partner of the “Born in Artsakh” ProgramHow to Protect Your Bank Card Data Ucom Subscribers can Benefit from 5G Network in More than 40 CountriesAmeriabank's MyInvest Platform Gains Direct Access to AMXTrader Trading System With Support of Ucom New EdPad Educational Tablet Piloted in ArmeniaAraratBank holds Annual General Meeting of ShareholdersIDBank and Henley & Partners Successfully Held the “Invest Beyond Borders: Global Mobility & Private Banking” Event in YerevanMoody's upgrades long-term deposit ratings of Unibank to B1, outlook stable
Society

How is the largest solar power plant in Armenia built?

Armenia's largest solar power facility is under construction in the Gegharkunik region. Shtigen Group undertook the building of the Masrik-1 solar plant, which has a capacity of 62 MW and covers 130 hectares. The construction phase began in November 2023. The work did not halt in winter, harsh cold, spring, or slush and rain; the Shtigen team was likewise prepared for whatever the climate was.

The construction project employed more than 130 workers, including those from Metz Masrik.

The Masrik-1 solar plant will generate 128,332 GWh of electricity per year, enough to power over 20,000 houses. In addition, this amount will prevent the release of more than 54,000 tons of carbon dioxide every year. By the way, 114,984 solar panels were used to build the station.

The construction procedure adheres to international standards, as confirmed by both local and foreign specialists.

The geographical scope of collaboration in the plant's development is as extensive as the project itself. The Masrik-1 project is owned by FRV Fotowatio Renewable Ventures, a leading global renewable energy development company, by establishing a partnership with Chinese contracting company CMEC and assigning construction work to Shtigen․